Research Article

Design Change and Operational Consideration of the HVAC System during Nuclear Power Plant Decommissioning

Table 2

Design considerations for decommissioning.

SystemRemoveMaintenanceNew installation

RCB HVAC and purgeRCFC (2 EA), CEDM cooling fan, reactor cavity fanRCFC (2 EA), SG enclosure R/C fan, annulus area R/C fan, all of purge system, ESFAS or alternativePortable temporary HVAC units, air discharge and intake duct for RCB purge system on each floor, duct for portable temporary HVAC units
FHB HVACā€”All system, ESFASā€”
MCR HVACSupply AHU (1 train), emergency make up ACU (2 trains), smoke removal fan, MCR recirculation duct, ESFASSupply AHU (1 train), exhaust fanTemporary HVAC units