BIM-Based Digital Fabrication Process for a Free-Form Building Project in South Korea

Table 6

Comparison of performance indicators in the queuing model.

Performance indicatorsCase projects [40]Specialty contractor (9,504 h)
Project 1Project 2Project 3Project 4

Period (day)352286308374154
No. of workers 21139
Mean arrival rate 1.0820.7481.0940.82626.17
Mean service rate 2311.6737.84
Server utilization 0.2710.2491.0940.1650.81
Server efficiency 0.7290.751N/A0.8350.19