BIM-Based Digital Fabrication Process for a Free-Form Building Project in South Korea
Table 6
Comparison of performance indicators in the queuing model.
| Performance indicators | Case projects [40] | Specialty contractor (9,504 h) | Project 1 | Project 2 | Project 3 | Project 4 |
| Period (day) | 352 | 286 | 308 | 374 | 154 | No. of workers | 2 | 1 | 1 | 3 | 9 | Mean arrival rate | 1.082 | 0.748 | 1.094 | 0.826 | 26.17 | Mean service rate | 2 | 3 | 1 | 1.67 | 37.84 | Server utilization | 0.271 | 0.249 | 1.094 | 0.165 | 0.81 | Server efficiency | 0.729 | 0.751 | N/A | 0.835 | 0.19 |
|
|