Fuzzy Multicriteria Decision-Making Model for Time-Cost-Risk Trade-Off Optimization in Construction Projects
Table 6
Activity duration.
Activity
Optimistic time
Moderate time
Pessimistic time
A
26
28
30
B
40
42
46
C
36
38
40
D
83
85
87
E
18
20
22
F
22
25
28