Main construction schedule for the Langyashan CFRD.
| Time arrangements | Construction procedures | Duration (day) |
| 2003.5.1∼2004.8.26 | Dam body filling | 474 | 2004.8.27∼2005.3.1 | Consolidation | 186 | 2005.3.2∼2005.5.18 | Concreting of face slab | 18 |
|
|