Proportion of shaft and toe resistance under working load.

P105P66P12

RW(100%)RE(100%)RS(100%)RW(100%)RE(100%)RS(100%)RW(100%)RE(100%)RS(100%)

6.250.00100.0010.000.00100.0014.290.00100.00
12.500.00100.0020.000.1999.8121.430.00100.00
18.750.00100.0030.000.3999.6128.570.6399.38
25.000.1399.8740.000.6699.3435.710.8399.17
31.250.2199.7950.001.8098.2042.861.1598.85
37.500.2799.7360.005.1894.8350.001.4698.54
43.750.3099.7070.0013.3286.6857.145.8494.16
50.000.3399.6780.0018.7081.3064.299.2590.75
56.250.5399.4790.0019.5680.4471.4311.8488.17
62.500.7599.25100.0020.2979.7178.5715.7684.24
68.750.9299.0885.7122.1877.83
75.001.0298.9892.8629.0770.93
81.251.1998.81100.0034.0165.99
87.501.2698.74
93.751.4798.53
100.001.8098.20

Note. RW = working load proportion; RE = end bearing percentage; RS = shaft resistance percentage.