Bearing Repair and Monitoring for Poyanghu Cable-Stayed Bridge

Table 1

Details of repair process and monitoring practices.

StepTimeLocation of the repaired bearingSpecific worksMonitored displacement directionsMonitored cables

119∼20 SeptemberDownstream sideEstablish temporary supportsLongitudinal, transverse, and vertical directions1#∼3#,
1′#∼3′#
225 SeptemberDownstream sideRemove temporary supports, apply heavy vehicles, and tension anchoring bolts arranged between main girder and bearingsLongitudinal, transverse, and vertical directions1#∼3#,
1′#∼3′#
312∼24 OctoberUpstream sideRemove the damaged anchoring bolts and ream holesLongitudinal, transverse, and vertical directions1#∼3#,
1′#∼3′#
425 OctoberUpstream sideApply heavy vehicles and tension anchoring bolts arranged between the main girder and the bearingsLongitudinal, transverse, and vertical directions