Bearing Repair and Monitoring for Poyanghu Cable-Stayed Bridge
Table 1
Details of repair process and monitoring practices.
| Step | Time | Location of the repaired bearing | Specific works | Monitored displacement directions | Monitored cables |
| 1 | 19∼20 September | Downstream side | Establish temporary supports | Longitudinal, transverse, and vertical directions | 1#∼3#, | 1′#∼3′# | 2 | 25 September | Downstream side | Remove temporary supports, apply heavy vehicles, and tension anchoring bolts arranged between main girder and bearings | Longitudinal, transverse, and vertical directions | 1#∼3#, | 1′#∼3′# | 3 | 12∼24 October | Upstream side | Remove the damaged anchoring bolts and ream holes | Longitudinal, transverse, and vertical directions | 1#∼3#, | 1′#∼3′# | 4 | 25 October | Upstream side | Apply heavy vehicles and tension anchoring bolts arranged between the main girder and the bearings | Longitudinal, transverse, and vertical directions | |
|
|