Constructing a Risk-Sharing Framework for Sponge City PPP Projects from the Perspective of the Individual Participant

Table 6

Initial risk sharing result.

Risk-bearing typeIndicators of the riskParticipant(s) bearing the risk

Risk taken separatelyTime delay (c9), lack of technical ability (c10), and change due to poor design (c11).WGCCD
Government intervention (c1), government default (c2), immature law and regulations (c3), and government inaction (c4)WSCC
Lack of management experience (c13) and unreasonable operating technology (c16)WCS

Shared riskProject financing failure (c5)WSCC, WIS, and FI
Interest rate (c6) and market price change (c7)WIS and WCS
Cost overspending (c8)WSCC, WGCCD, WIS, and WCS
Insufficient operating income (c14) and lack of an effective payment mechanism (c15)WSCC and WCS