Experimental Behavior of the Curved Continuous Twin I-Girder Composite Bridge with a Precast Concrete Slab Subjected to Bending, Shear, and Torsion
Table 4
Construction sequence of the bridge model and prototype bridge.
| Construction sequence | Prototype bridge | Bridge model |
| Step 1 | Lifting the first span steel main girder (40 m) | Lifting the first span steel main girder (8 m) and hanging weight compensation sandbags | Step 2 | Lifting the second span steel main girder (30 m) and welding two-span girder together | Lifting the second span steel main girder (6 m), hanging weight compensation sandbags, and welding two-span girder together | Step 3 | Installing precast concrete slabs in sequence | Installing precast concrete slabs in sequence and hanging weight compensation sandbags | Step 4 | Pouring concrete in the shear pocket and transverse joints | Pouring concrete in the shear pocket and transverse wet joints | Step 5 | Completing the deck pavement | Loading pavement weight sandbags |
|
|