Experimental Behavior of the Curved Continuous Twin I-Girder Composite Bridge with a Precast Concrete Slab Subjected to Bending, Shear, and Torsion

Table 4

Construction sequence of the bridge model and prototype bridge.

Construction sequencePrototype bridgeBridge model

Step 1Lifting the first span steel main girder (40 m)Lifting the first span steel main girder (8 m) and hanging weight compensation sandbags
Step 2Lifting the second span steel main girder (30 m) and welding two-span girder togetherLifting the second span steel main girder (6 m), hanging weight compensation sandbags, and welding two-span girder together
Step 3Installing precast concrete slabs in sequenceInstalling precast concrete slabs in sequence and hanging weight compensation sandbags
Step 4Pouring concrete in the shear pocket and transverse jointsPouring concrete in the shear pocket and transverse wet joints
Step 5Completing the deck pavementLoading pavement weight sandbags