Construction Quality Control Study of Double-Layer Continuous Paving for Large-Thickness Cement-Stabilized Base
Table 10
Compaction process of double-layer continuous paving base.
| Position | Usage | Compaction method | Rolling speed (km/h) |
| Lower base | Initial pressure | Static compaction 1 time | 1.5∼1.7 | Repress | One weak and three strong | 1.8∼2.0 | Final pressure | Rubber wheel 1 time | 2.0∼2.5 |
| Upper base | Initial pressure | Static compaction 1 time | 1.5∼1.7 | Repress | One weak, one strong, and three weak | 1.5∼1.8 | Final pressure | Rubber wheel 1 time | 2.0∼2.5 |
|
|