Construction Quality Control Study of Double-Layer Continuous Paving for Large-Thickness Cement-Stabilized Base

Table 2

Design of pull strength test of core sample.

Simulate layered discontinuous pavingSimulate layered continuous paving

In accordance with the “Testing Rules for Highway Engineering Inorganic Binder Stabilizing Materials” (JTG E51-2009), the test pieces with the size of Φ150 mm × 150 mm were molded.

Weigh half of the mixture to make a test piece. After being demolded, the test piece was cured for 7 days. After that, put the test piece back into the test mold, spread a layer of cement paste on the surface, and then pour the other half of the same quality mixture, compact and curing for 7 d.Weigh half of the mixture and pour it into the test mold, put into a pad for compaction, remove the pad after 1 hour, and pour the remained mixture into the mold, compact and curing for 7 d.