| Code | Strategies | Component clusters |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|
| | A: resources (R) | | | | | | | |
| OS1 | Establish and provide support to firms to access finance and loan | | | | | | | 0.814 |
| OS4 | Invest in technology and establish technology transfer centre | | | | | | | 0.838 |
| OS19 | Employ competent and technical employees | | | | | | | 0.861 |
| OS5 | Optimization of local quality construction materials | | | | | | | 0.763 |
| OS18 | Establish construction equipment centre | | | | | | | 0.891 |
| | B: capability building (CB) | | | | | | | |
| OS6 | Facilitate training for capacity building | | 0.705 | | | | | |
| OS10 | Enhance networking to share experience | | 0.669 | | | | | |
| OS7 | Adopt joint venture and partnership with an overseas firm | | 0.886 | | | | | |
| | C: operational (O) | | | | | | | |
| OS11 | Ensure resource availability, allocation, and utilization | | | 0.631 | | | | |
| OS3 | Adhere to low firm operational cost | | | 0.787 | | | | |
| OS13 | Ensure employee’s right working environment | | | 0.789 | | | | |
| OS2 | Adopt a low bidding price strategy | | | 0.771 | | | | |
| | D: government policy (G) | | | | | | | |
| OS17 | Policy on compulsory joint venture | | | | | | 0.696 | |
| OS12 | Training certification by government | | | | | | 0.595 | |
| OS9 | Implement tax reduction policy of imported equipment and materials | | | | | | 0.741 | |
| OS8 | Policy formulation of construction bank establishment | | | | | | 0.740 | |
| | E: design (D) | | | | | | | |
| SCP1 | Employ a competent design expert | | | | 0.800 | | | |
| SCP21 | Gather a complete design requirement for client and stakeholders | | | | 0.681 | | | |
| SCP4 | Allocate a balanced design resources | | | | 0.723 | | | |
| SCP2 | Integrate design team with another related department | | | | 0.729 | | | |
| | F: procurement (P) | | | | | | | |
| SCP15 | Reviewing the conflicting procurement policy, laws, and regulations | | | | | 0.791 | | |
| SCP11 | Adopt an electronic-tendering system to reduce a bidding cycle time | | | | | 0.698 | | |
| SCP7 | Adherence to procurement ethics and code of conduct | | | | | 0.717 | | |
| | G: construction management (CM) | | | | | | | |
| SCP10 | Resource (finance, schedule, material, and equipment) management | 0.903 | | | | | | |
| SCP18 | Quality assurance (standard and specification) | 0.798 | | | | | | |
| SCP12 | Select a competent, experienced, and accessible contractors | 0.789 | | | | | | |
| SCP16 | Adoption of modern construction technique | 0.762 | | | | | | |
| | Note: (1) initial eigenvalues | 6.887 | 3.328 | 1.422 | 1.316 | 1.184 | 1.017 | 1.279 |
| | (2) Percentage of variance (%) | 31.306 | 15.129 | 6.464 | 5.984 | 5.383 | 4.625 | 4.431 |
| | (3) Cumulative percentage of initial eigenvalues | 31.306 | 46.435 | 52.899 | 58.883 | 64.265 | 68.890 | 73.321 |
|