Causes of Delay in the Construction Projects of Subway Tunnel

Table 1

List of delay causes and related classification.

Main classificationCauses under each classification

(1) OwnerLate issuing the approval documents by the owner
Change orders by the owner during construction period
Poor communication between the owner and other construction parties
Postponement of the project by the owner
Progressing payments delay by the owner
Delays in decision making by the owner
Delay in providing construction materials
Poor financial status of the owner
Late land handover to the contractor by the owner
Undefined scope of working

(2) DesignerInappropriate design
Late design works
Mistake in design

(3) ContractorImproper construction method
Poor site supervision by the contractor
Rework because of errors during construction
Ineffective scheduling of the project by the contractor
Conflict between the contractor and other parties
Difficulties in financing the project by the contractor
Poor resource management
Poor communication by the contractor with other construction parties

(4) ConsultantIncapable and Insufficient inspectors
Poor communication between the consultant and other construction parties
Inflexibility of the consultant
Delay of inspection by the consultant

(5) LaborInsufficient laborers
Personal conflicts among laborers
Low skill level of equipment-operator
Low productivity of laborers
Conflict between laborers and management team

(6) EnvironmentPoor terrain condition and wall rock quality
Natural disaster
Weather condition
Poor effect on the drainage system
Complicated geological conditions

(7) EquipmentLack of equipment efficiency
Shortage of advanced large equipment
Serious damage to the equipment

(8) MaterialChanges in material types and specifications during construction
Shortage in construction material
Material loss in the process of transportation
Increasing prices of raw materials

(9) External factorsAward the project to lowest bid price
Changing of bankers’ policy for loans
Limited construction area
Inconvenient site access
National policy for subway tunnel construction
Lag in technology
Disturbance to public activities