Research Article
Causes of Delay in the Construction Projects of Subway Tunnel
Table 10
Ranking of the causes from external factors.
| Cause | View of consultants | View of contractors | Combined view | Rank | Severity index | Rank | Severity index | Rank | Severity index |
| National policy for subway tunnel construction | 1 | 73.81 | 1 | 76.52 | 1 | 75.17 | Award the project to lowest bid price | 2 | 71.16 | 2 | 72.05 | 2 | 71.61 | Limited construction area | 4 | 62.93 | 3 | 67.34 | 3 | 65.14 | Lag in technology | 3 | 65.50 | 4 | 63.21 | 4 | 64.36 | Changing of bankers’ policy for loans | 5 | 52.72 | 6 | 50.37 | 5 | 51.55 | Inconvenient site access | 6 | 47.06 | 5 | 52.30 | 6 | 49.68 | Disturbance to public activities | 7 | 44.25 | 7 | 46.19 | 7 | 45.22 |
|
|