Causes of Delay in the Construction Projects of Subway Tunnel
Table 14
Top six causes in agreement between consultants and contractors.
| Cause | Overall rank | Severity index | Absolute difference in severity index | Consultants’ view | Contractors’ view |
| Postponement of the project by the owner | 8 | 68.21 | 68.38 | 0.17 | Conflict between laborers and management team | 40 | 46.91 | 47.39 | 0.48 | Complicated geological conditions | 2 | 74.38 | 73.62 | 0.76 | Delays in decision making by the owner | 14 | 64.56 | 63.76 | 0.80 | Award the project to lowest bid price | 4 | 71.16 | 72.05 | 0.89 | Progressing payments delay by the owner | 3 | 71.72 | 72.65 | 0.93 |
|
|