Research Article

Causes of Delay in the Construction Projects of Subway Tunnel

Table 14

Top six causes in agreement between consultants and contractors.

CauseOverall rankSeverity indexAbsolute difference in severity index
Consultants’ viewContractors’ view

Postponement of the project by the owner868.2168.380.17
Conflict between laborers and management team4046.9147.390.48
Complicated geological conditions274.3873.620.76
Delays in decision making by the owner1464.5663.760.80
Award the project to lowest bid price471.1672.050.89
Progressing payments delay by the owner371.7272.650.93