Research Article

Causes of Delay in the Construction Projects of Subway Tunnel

Table 15

Top six causes in disagreement between consultants and contractors.

CauseOverall rankSeverity indexAbsolute difference in severity index
Consultants’ viewContractors’ view

Poor site supervision by the contractor4441.1848.026.84
Poor communication between the consultant and other construction parties4249.2541.577.68
Poor communication between the owner and other construction parties3057.9548.99.05
Weather condition3446.1455.79.56
Late land handover to the contractor by the owner2366.2555.5310.72
Poor communication by the contractor with other construction parties3147.1859.2212.04