Research Article
Causes of Delay in the Construction Projects of Subway Tunnel
Table 15
Top six causes in disagreement between consultants and contractors.
| Cause | Overall rank | Severity index | Absolute difference in severity index | Consultants’ view | Contractors’ view |
| Poor site supervision by the contractor | 44 | 41.18 | 48.02 | 6.84 | Poor communication between the consultant and other construction parties | 42 | 49.25 | 41.57 | 7.68 | Poor communication between the owner and other construction parties | 30 | 57.95 | 48.9 | 9.05 | Weather condition | 34 | 46.14 | 55.7 | 9.56 | Late land handover to the contractor by the owner | 23 | 66.25 | 55.53 | 10.72 | Poor communication by the contractor with other construction parties | 31 | 47.18 | 59.22 | 12.04 |
|
|