Causes of Delay in the Construction Projects of Subway Tunnel

Table 16

Severity index difference of the top six causes between consultants and contractors.

CauseOverall rankSeverity indexAbsolute difference in severity index
Consultants’ viewContractors’ view

National policy for subway tunnel construction173.8176.522.71
Complicated geological conditions274.3873.620.76
Progressing payments delay by the owner371.7272.650.93
Award the project to lowest bid price471.1672.050.89
Shortage of advanced large equipment569.5271.081.56
Low productivity of laborers668.2570.62.35