Causes of Delay in the Construction Projects of Subway Tunnel
Table 16
Severity index difference of the top six causes between consultants and contractors.
| Cause | Overall rank | Severity index | Absolute difference in severity index | Consultants’ view | Contractors’ view |
| National policy for subway tunnel construction | 1 | 73.81 | 76.52 | 2.71 | Complicated geological conditions | 2 | 74.38 | 73.62 | 0.76 | Progressing payments delay by the owner | 3 | 71.72 | 72.65 | 0.93 | Award the project to lowest bid price | 4 | 71.16 | 72.05 | 0.89 | Shortage of advanced large equipment | 5 | 69.52 | 71.08 | 1.56 | Low productivity of laborers | 6 | 68.25 | 70.6 | 2.35 |
|
|