Causes of Delay in the Construction Projects of Subway Tunnel
Table 17
Ranking of main classifications.
| Classification | View of consultants | View of contractors | Combined view | Rank | Classification severity index | Rank | Classification severity index | Rank | Classification severity index |
| Owner | 3 | 62.55 | 4 | 59.69 | 3 | 61.12 | Designer | 9 | 46.59 | 8 | 50.26 | 9 | 48.43 | Contractor | 7 | 51.72 | 7 | 54.71 | 7 | 53.21 | Consultant | 8 | 49.39 | 9 | 49.15 | 8 | 49.27 | Labor | 5 | 58.12 | 5 | 58.34 | 5 | 58.23 | Environment | 6 | 53.62 | 6 | 54.88 | 6 | 54.25 | Material | 2 | 62.70 | 3 | 60.59 | 2 | 61.65 | Equipment | 1 | 66.41 | 1 | 65.96 | 1 | 66.19 | External factor | 4 | 59.63 | 2 | 61.14 | 4 | 60.39 |
|
|