Causes of Delay in the Construction Projects of Subway Tunnel

Table 17

Ranking of main classifications.

ClassificationView of consultantsView of contractorsCombined view
RankClassification severity indexRankClassification severity indexRankClassification severity index

Owner362.55459.69361.12
Designer946.59850.26948.43
Contractor751.72754.71753.21
Consultant849.39949.15849.27
Labor558.12558.34558.23
Environment653.62654.88654.25
Material262.70360.59261.65
Equipment166.41165.96166.19
External factor459.63261.14460.39