Causes of Delay in the Construction Projects of Subway Tunnel

Table 3

Ranking of the causes from the owner.

CauseView of consultantsView of contractorsCombined view
RankSeverity indexRankSeverity indexRankSeverity index

Progressing payments delay by the owner171.72172.65172.19
Postponement of the project by the owner268.21368.38268.30
Delay in providing construction materials366.47269.36367.92
Delays in decision making by the owner564.56463.76464.16
Change orders by the owner during construction period662.25560.82561.54
Late land handover to the contractor by the owner466.25755.53660.89
Poor financial status of the owner761.12658.67759.90
Poor communication between the owner and other construction parties857.95948.90853.43
Undefined scope of working954.62851.03952.83
Late issuing the approval documents by the owner1052.381047.831050.11