Research Article
Causes of Delay in the Construction Projects of Subway Tunnel
Table 3
Ranking of the causes from the owner.
| Cause | View of consultants | View of contractors | Combined view | Rank | Severity index | Rank | Severity index | Rank | Severity index |
| Progressing payments delay by the owner | 1 | 71.72 | 1 | 72.65 | 1 | 72.19 | Postponement of the project by the owner | 2 | 68.21 | 3 | 68.38 | 2 | 68.30 | Delay in providing construction materials | 3 | 66.47 | 2 | 69.36 | 3 | 67.92 | Delays in decision making by the owner | 5 | 64.56 | 4 | 63.76 | 4 | 64.16 | Change orders by the owner during construction period | 6 | 62.25 | 5 | 60.82 | 5 | 61.54 | Late land handover to the contractor by the owner | 4 | 66.25 | 7 | 55.53 | 6 | 60.89 | Poor financial status of the owner | 7 | 61.12 | 6 | 58.67 | 7 | 59.90 | Poor communication between the owner and other construction parties | 8 | 57.95 | 9 | 48.90 | 8 | 53.43 | Undefined scope of working | 9 | 54.62 | 8 | 51.03 | 9 | 52.83 | Late issuing the approval documents by the owner | 10 | 52.38 | 10 | 47.83 | 10 | 50.11 |
|
|