Causes of Delay in the Construction Projects of Subway Tunnel
Table 4
Ranking of the causes from designer.
| Cause | View of consultants | View of contractors | Combined view | Rank | Severity index | Rank | Severity index | Rank | Severity index |
| Late design works | 1 | 52.51 | 1 | 58.26 | 1 | 55.39 | Mistake in design | 2 | 46.58 | 2 | 49.35 | 2 | 47.97 | Inappropriate design | 3 | 40.69 | 3 | 43.17 | 3 | 41.93 |
|
|