Causes of Delay in the Construction Projects of Subway Tunnel
Table 5
Ranking of the causes from the contractor.
| Cause | View of consultants | View of contractors | Combined view | Rank | Severity index | Rank | Severity index | Rank | Severity index |
| Ineffective scheduling of the project by the contractor | 1 | 65.60 | 2 | 62.30 | 1 | 63.95 | Conflict between the contractor and other parties | 2 | 61.28 | 1 | 62.82 | 2 | 62.05 | Difficulties in financing the project by the contractor | 3 | 61.01 | 3 | 61.95 | 3 | 61.48 | Poor communication by the contractor with other construction parties | 5 | 47.18 | 4 | 59.22 | 4 | 53.20 | Rework because of errors during construction | 4 | 48.71 | 5 | 50.75 | 5 | 49.73 | Improper construction method | 6 | 46.38 | 7 | 47.36 | 6 | 46.87 | Poor site supervision by the contractor | 8 | 41.18 | 6 | 48.02 | 7 | 44.60 | Poor resource management | 7 | 42.40 | 8 | 45.24 | 8 | 43.82 |
|
|