Causes of Delay in the Construction Projects of Subway Tunnel
Table 6
Ranking of the causes from the consultant.
| Cause | View of consultants | View of contractors | Combined view | Rank | Severity index | Rank | Severity index | Rank | Severity index |
| Delay of inspection by the consultant | 1 | 57.58 | 2 | 54.69 | 1 | 56.14 | Inflexibility of the consultant | 2 | 53.86 | 1 | 56.82 | 2 | 55.34 | Poor communication between the consultant and other construction parties | 3 | 49.25 | 4 | 41.57 | 3 | 45.41 | Incapable and insufficient inspectors | 4 | 36.85 | 3 | 43.52 | 4 | 40.19 |
|
|