Causes of Delay in the Construction Projects of Subway Tunnel

Table 7

Ranking of the causes from labor.

CauseView of consultantsView of contractorsCombined view
RankSeverity indexRankSeverity indexRankSeverity index

Low productivity of laborers168.25170.60169.43
Insufficient laborers361.87265.42263.65
Low skill level of equipment-operator263.18361.75362.47
Personal conflicts among laborers450.37546.52448.45
Conflict between laborers and management team546.91447.39547.15