Causes of Delay in the Construction Projects of Subway Tunnel

Table 9

Ranking of the causes from equipment and material.

CauseView of consultantsView of contractorsCombined view
RankSeverity indexRankSeverity indexRankSeverity index

Shortage of advanced large equipment369.52171.08170.30
Shortage in construction material171.05265.71268.38
Lack of equipment efficiency269.85364.49367.17
Changes in material types and specifications during construction463.26561.90462.58
Serious damage to the equipment659.85462.31561.08
Increasing prices of raw materials756.30659.47657.89
Material loss in the process of transportation560.17755.28757.73