Dynamic Probability Analysis for Construction Schedule Using Subset Simulation
Table 1
Schedule network failure evaluation comparison (deadline = 85 days).
| | Methods | Failure probability (%) | Variation coefficient | Running time (sec.) |
| | MCPM | LUBE | 1.93 | N/A | 0.00 | | FCPM | Triangular | 19.57 | N/A | 0.00 | | PCPM | Direct MCS | 2.25 | 2.45% | 2.58 | | Our method | 2.24 | 3.11% | 0.35 |
|
|