Temperature Control Technology for Construction of Jinsha River Bridge
Table 6
Analysis of measured results of cap temperature.
| Serial number | Temperature control item | Control standard | Measured value of first pouring (°C) | Measured value of second pouring (°C) |
| 1 | Temperature of pouring concrete | ≤26°C | 25∼30 | 24∼28.5 | 2 | Maximum temperature of internal concrete | ≤65°C | 64.5 | 61.6 | 3 | Temperature difference between the inner surface of concrete pouring body (including equivalent temperature of concrete shrinkage) | ≤28°C | 26.6 | 24.6 | 4 | The rate of cooling of inside concrete | ≤2.0°C/d | 2.1 | 1.98 | 5 | Temperature difference between surface of concrete and atmosphere | ≤20°C | 16.1 | 17.1 | 6 | Temperature difference between inlet and outlet of cooling water | ≤10°C | — | 9.8 | 7 | The temperature difference between the cooling water and the inside concrete when the water is first supplied or resupplied after interruption | ≤25°C | 24.8 | — | 8 | Temperature difference between curing water and concrete surface | ≤15°C | True | True |
|
|