Research Article

Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia

Table 2

Risk factors leading to schedule delays in infrastructure projects.

CategoryRisks leading to cost overrunRef.

Client/owner relatedUnrealistic contract durations imposed by owner[7, 39]
Poorly defined scope[9, 16]
Client/owner interference[22, 33, 39]
Variations (design changes/extra work)[38]
Poor communication between project team[37, 40]
Slow decision making by owner[33]

Consultant relatedDelays in payments[5, 41]
Underestimation of project cost[37, 40]
Poor inspection or supervision[15]
Poor contract management[40]
Delay in preparation and approval of drawings[5, 38]
Waiting time for approval of tests and inspections[33, 37]
Lack of competency and experience of consultant[9, 20, 33]

Contractor relatedPoor site management[28, 37]
Financial problems/constraints[5, 35, 37]
Construction methods[9, 33]
Poor planning (materials and labor estimation)[3, 15, 38]
Poor communication and misunderstanding[6, 17, 35]
Subcontractors (lack of experience, etc.)[7, 33]
Inadequate experience and competency of contractor[5, 35, 41]

Government relatedSlow permits by government agencies[9, 20]
Bureaucracies in government agencies[9]
Political interference[5, 7]
Economic conditions (currencies, inflation)[7, 25]
Ineffective legislative regulations[33]

Materials relatedShortage of construction materials[5, 15]
Escalation of material prices[39]
Delay of material delivery on-site[28, 32, 33]
Poor material procurement techniques[7, 37]
Low quality of materials[9, 25, 35]

Contractual relatedMajor claims and disputes[17]
Inappropriate type of contract (procurement process)[7, 9, 20]
Poor collaboration between parties[20, 33]