Cost data for road projects in Ethiopia.

ProjectsProject costCost overrun (%)

Meri, Shashemene, Hawassa197170297.9217
Dedebit, Adiremet810212552.6117
Injibara, Chagni Pawi Junction, Fendika, Ayema1337718925.9310
Kibremengist, Shakiso119673513.6961
Koka, Adulala, Debrezeit613165000.0029
Hawassa Chuko (Mombasa, A.A Corridor)965247145.4825
Chenka, Dembidolo Road648548842.214
Ayira, Chanka Road669143993.901
Abi Adi, Fireweyni819419501.067
South f6 junction, f4 junction1399064061.645
Mekeranjo, Ayira633534840.484
Jimma, Mizan742938243.7820
Dire Dawa, Melka Jebdu470000000.008
Abunepetros square, Pastor144440764.434.11
Dama Hotel, Hanamariam5421400326.47
Gotera, Wellosefer300000008.17
Megenagna, Ayat224055813.118.32
Megenagna, Meskel Square, Torhiloch lot 1 & lot 211624489014.49
Mekanisa roundabout, Addis36554500.4613.95
Meskel flower, Bole Rwanda49587265.6358.42
Shola Gebeya, Lemhotel, Anbessa Garage109512767.932.69
Winget Aseco Bridge154,485,787.4117.25
Yekatit 12 square, Afenchober, Semen Hotel3621357950.04
Bedele, Metu Road Upgrading Project610,019,298.3516
Kombolcha, Burka1,588,240,440.604
Tsegede Junction, Ketema Nigus516,442,158.882