Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia

Table 6

Time data for road construction projects.

Road projectsContract duration (days)Time elapsed (delay)Percentage (delay) (%)

Shekussen, Michola365499137
Meri, Shashemene, Hawassa770924120
Dedebit, Adiremet109550146
Injibara, Chagni Pawi Junction, Fendika, Ayema91372179
Kibremengist, Shakiso5401035192
Koka, Adulala, Debrezeit73033045
Hawassa Chuko (Mombasa, A.A Corridor)730756104
Chenka, Dembidolo Road910911100
Ayira, Chanka Road91062068
Abi Adi, Fireweyni109579973
South f6 junction, f4 junction1095343
Mekeranjo, Ayira91039844
Jimma, Mizan10361832177
Dire Dawa - Melka Jebdu54837769
Dolo Ojo Junction, Hargale73036650
Winget, Aseco Bridge330718217.58
Yekatit 12 square, Afenchober, Semen Hotel365965264.38
Dama Hotel, Hanamariam365790216.44
Megenagna, Meskel Square, Torhiloch lot 1 & lot 255017632.00
Meskel flower, Bole Rwanda5751,795312.17
Shola Gebeya, Lemhotel, Anbessa Garage575657114.26
Mekanisa roundabout, Addis90180200.00
Abunepetros square, Pastuer224539240.63
Megenagna, Ayat42028968.81
Gotera, Wellosefer1804525.00
Gelan, Insilale, L/Dadhi109597589
Sheno, Deneba2036653
Kula, Dereba, Semar130046035
Shambo town int. Asphalt4501156257
Hinde Bridge450621138
Kurbi, Giwe, Dado9252400259
Hidi, Lola, Sololo109512011
Alge, Sachi, Mako, Degga730850116
Yayo, Elemo72064590
Gelila, Waja, Mender 10109548544
Bedele, Metu Road Upgrading Project1,080.00401.0037
Kombolcha, Burka1,095.00187.0017
Tsegede Junction, Ketema Nigus730.00554.0076