Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia

Table 7

Critical risks leading to cost overrun in construction projects.

Critical risks leading to cost overrunMean score
OverallContractorConsultantClientAcademia
Mean scoreRankMean scoreRankMean scoreRankMean scoreRankMean scoreRank

Inflation4.4314.4634.42254.33254.5025
Inaccurate cost estimates4.2924.3844.2583.8384.508
Variations4.2434.0894.0834.3334.173
Unforeseeable fluctuation in material and labor prices4.2444.6213.83273.83274.4427
Availability of resources (labor, materials, and equipment)4.1454.08113.50143.50144.1114
Delay in decision making4.1063.92123.9243.3344.174
Market conditions/economic climate4.1074.5424.00233.50233.8923
Political situation of the country4.1084.1583.58242.83244.1124
Delay in payment of completed works3.9594.1563.4223.0024.332
Lack of coordination and communication between parties3.95103.85134.1753.5054.285
Poor supervision and contract management3.86114.1574.2573.1774.117
Clarity and accuracy of project information before execution3.86124.08103.50113.50113.6711
Financial status of client3.81133.69183.6713.8314.061
Complexity of design and construction3.81143.15253.50123.83123.6112
Changes in project schedule and phasing requirements3.80153.62203.92173.83174.1717
Poor feasibility and project analysis3.71164.2354.0893.0094.399
Level of workmanship (productivity and performance)3.70173.83163.67223.33223.7822
Competency and experience of consulting firm3.57183.85143.1763.5063.836
Government regulations3.48193.23243.42263.33263.6126
Availability of machinery3.48203.77173.00282.33283.4428
Site constraints (access, storage, electricity)3.43213.54213.33163.17163.1716
Clear and detailed drawings and specification3.38223.62193.42103.50103.6110
Project delivery method and contractual arrangement3.38233.85153.33193.17193.1119
Quality of information flow during execution3.29243.46223.50133.17133.6113
Type of currency used3.00253.38233.08182.83183.2918
Advance payment arrangement2.90263.00273.33203.00202.9420
Type and value of insurance2.71272.85283.25213.33212.7221
Type of project (residential, commercial, industrial, etc.)2.67283.00262.75153.50152.9415