Critical risks leading to cost overrun | Mean score |
Overall | Contractor | Consultant | Client | Academia |
Mean score | Rank | Mean score | Rank | Mean score | Rank | Mean score | Rank | Mean score | Rank |
|
Inflation | 4.43 | 1 | 4.46 | 3 | 4.42 | 25 | 4.33 | 25 | 4.50 | 25 |
Inaccurate cost estimates | 4.29 | 2 | 4.38 | 4 | 4.25 | 8 | 3.83 | 8 | 4.50 | 8 |
Variations | 4.24 | 3 | 4.08 | 9 | 4.08 | 3 | 4.33 | 3 | 4.17 | 3 |
Unforeseeable fluctuation in material and labor prices | 4.24 | 4 | 4.62 | 1 | 3.83 | 27 | 3.83 | 27 | 4.44 | 27 |
Availability of resources (labor, materials, and equipment) | 4.14 | 5 | 4.08 | 11 | 3.50 | 14 | 3.50 | 14 | 4.11 | 14 |
Delay in decision making | 4.10 | 6 | 3.92 | 12 | 3.92 | 4 | 3.33 | 4 | 4.17 | 4 |
Market conditions/economic climate | 4.10 | 7 | 4.54 | 2 | 4.00 | 23 | 3.50 | 23 | 3.89 | 23 |
Political situation of the country | 4.10 | 8 | 4.15 | 8 | 3.58 | 24 | 2.83 | 24 | 4.11 | 24 |
Delay in payment of completed works | 3.95 | 9 | 4.15 | 6 | 3.42 | 2 | 3.00 | 2 | 4.33 | 2 |
Lack of coordination and communication between parties | 3.95 | 10 | 3.85 | 13 | 4.17 | 5 | 3.50 | 5 | 4.28 | 5 |
Poor supervision and contract management | 3.86 | 11 | 4.15 | 7 | 4.25 | 7 | 3.17 | 7 | 4.11 | 7 |
Clarity and accuracy of project information before execution | 3.86 | 12 | 4.08 | 10 | 3.50 | 11 | 3.50 | 11 | 3.67 | 11 |
Financial status of client | 3.81 | 13 | 3.69 | 18 | 3.67 | 1 | 3.83 | 1 | 4.06 | 1 |
Complexity of design and construction | 3.81 | 14 | 3.15 | 25 | 3.50 | 12 | 3.83 | 12 | 3.61 | 12 |
Changes in project schedule and phasing requirements | 3.80 | 15 | 3.62 | 20 | 3.92 | 17 | 3.83 | 17 | 4.17 | 17 |
Poor feasibility and project analysis | 3.71 | 16 | 4.23 | 5 | 4.08 | 9 | 3.00 | 9 | 4.39 | 9 |
Level of workmanship (productivity and performance) | 3.70 | 17 | 3.83 | 16 | 3.67 | 22 | 3.33 | 22 | 3.78 | 22 |
Competency and experience of consulting firm | 3.57 | 18 | 3.85 | 14 | 3.17 | 6 | 3.50 | 6 | 3.83 | 6 |
Government regulations | 3.48 | 19 | 3.23 | 24 | 3.42 | 26 | 3.33 | 26 | 3.61 | 26 |
Availability of machinery | 3.48 | 20 | 3.77 | 17 | 3.00 | 28 | 2.33 | 28 | 3.44 | 28 |
Site constraints (access, storage, electricity) | 3.43 | 21 | 3.54 | 21 | 3.33 | 16 | 3.17 | 16 | 3.17 | 16 |
Clear and detailed drawings and specification | 3.38 | 22 | 3.62 | 19 | 3.42 | 10 | 3.50 | 10 | 3.61 | 10 |
Project delivery method and contractual arrangement | 3.38 | 23 | 3.85 | 15 | 3.33 | 19 | 3.17 | 19 | 3.11 | 19 |
Quality of information flow during execution | 3.29 | 24 | 3.46 | 22 | 3.50 | 13 | 3.17 | 13 | 3.61 | 13 |
Type of currency used | 3.00 | 25 | 3.38 | 23 | 3.08 | 18 | 2.83 | 18 | 3.29 | 18 |
Advance payment arrangement | 2.90 | 26 | 3.00 | 27 | 3.33 | 20 | 3.00 | 20 | 2.94 | 20 |
Type and value of insurance | 2.71 | 27 | 2.85 | 28 | 3.25 | 21 | 3.33 | 21 | 2.72 | 21 |
Type of project (residential, commercial, industrial, etc.) | 2.67 | 28 | 3.00 | 26 | 2.75 | 15 | 3.50 | 15 | 2.94 | 15 |
|