Research Article

Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia

Table 8

Critical risks leading to schedule delays in construction projects.

Critical risks leading to schedule delayMean score
OverallContractorConsultantClientAcademia
Mean scoreRankMean scoreRankMean scoreRankMean scoreRankMean scoreRank

Variations (design changes/extra work)4.7114.5594.3334.5014.561
Economic conditions (currency, inflation)4.4824.9214.7514.6734.502
Escalation of material prices4.4834.5884.2554.1754.504
Shortage of construction materials4.3844.5854.4224.6724.173
Delay in payments4.3354.2533.8393.50214.225
Financial problems/constraints4.3364.67144.08173.50224.1717
Delay in preparation and approval of drawings4.2974.25154.3343.67174.0626
Poor site management4.2484.5844.1763.50123.8315
Poor planning (material and labor estimation)4.2494.6764.1773.83234.0029
Construction methods4.14104.3323.83123.5044.066
Delay of material delivery on-site4.14114.75123.92184.50244.119
Unrealistic contract durations imposed by owner4.1124.25103.75133.50254.0023
Underestimation of project cost4.1134.42163.92223.17314.1130
Poorly defined project scope4.05144.4274.00103.67104.1713
Slow decision making by owners4.05154.58113.75234.00183.8931
Poor communication between project team4164.08193.92144.1763.947
Inadequate experience and competency of contractor4174.00213.83194.1773.7214
Lack of experience of consulting firm3.95183.83254.1783.33283.5632
Waiting time for approval of tests and inspections3.86193.83134.00113.5083.7810
Poor communication and misunderstandings3.86204.17173.75243.83133.8911
Bureaucracy in government agencies3.86214.33223.58274.17264.1722
Poor collaboration between major parties3.86224.00263.67323.00323.9427
Subcontractors (lack of experience, etc.)3.76234.09183.67203.67143.618
Poor material procurement techniques3.76244.08203.83283.83194.1124
Owner interference3.71253.91233.67153.8393.7816
Poor inspection/supervision3.71263.75243.75253.50154.1118
Ineffective legislative regulations3.71273.67293.67294.17273.9420
Major claims and disputes3.71283.92303.92303.33293.5325
Inappropriate type of contract (procurement process)3.67293.83273.67313.33303.7828
Slow permits by government agencies3.62303.83283.83213.83113.6712
Political interference3.62313.67313.75264.00163.5619
Low quality of materials3.48323.33323.92163.67203.7221