Research Article
Analysis of Cost Overrun and Schedule Delays of Infrastructure Projects in Low Income Economies: Case Studies in Ethiopia
Table 9
Critical recommended actions to reduce cost overrun and delay.
| Stakeholder | Key recommended actions (checklists) |
| Client | (i) Client should allocate proper budget as per the cost estimation including contingency | (ii) Owner should appoint a separate construction management consultant for quick decision making, particularly for major projects | (iii) Scope of projects shall be adequately defined | (iv) Reduce variations and change orders after comment of projects |
| Contractor | (i) Resource planning, including equipment and labor, should be done as per project milestone and duration | (ii) Provide various capacity building trainings and motivation incentives for workers | (iii) Develop proper work methodology to improve productivity of labors and equipment | (iv) Develop project specific hierarchical structure to facilitate decision making between project team | (v) Use appropriate innovations and technologies to improve performance of infrastructure projects |
| Consultant | (i) Provide complete design and cost estimation as per the requirement by owners | (ii) Develop mechanisms to solve disputes between client and contractor | (iii) Develop project specific strategies to monitor progress of projects and inspect key developments | (iv) Approve interim payments and design changes in line with contract documents and specifications |
|
|