Crane Lifting Optimization and Construction Monitoring in Steel Bridge Construction Project Based on BIM and UAV
Table 1
Detailed information on the steel bridge.
| Pier number | No. 72∼No. 75 | Mileage station | K13 + 374.783∼K13 + 444.783 | Span length | 47.3 m + 70 m + 62.3 m | Superstructure | Steel box bridge with continuous girder | Overall length of the bridge | 179.6 m | Design speed | 80 km/h | Cross section | 0.5 m (guard fence) + 11.75 m (lanes) + 0.5 m (median divide) + 11.75 m (lanes) + 0.5 m (guard fence) = 25 m | Design reference period | 100 years |
|
|