Research on Reasoning concerning Emergency Measures for Industrial Project Scheduling Control
Table 10
Preventive measures.
Scheme
Measure
Strengthening the principle of the design scheme
In the early detailed design stage, the design basis of the basic design should be confirmed, and the process frame should be designed with a steel structure.
Strengthening the procurement planning for key long-term equipment
In the procurement planning stage, the reactor should be designated as key long-term equipment, and a detailed reactor procurement plan should be developed. Corresponding nodes such as contract signing and arrival time should be specified in the technical agreement portion of the reactor procurement contract.
Strengthening the planning of the construction scheme
In the pipeline installation stage, the pipeline installation scheme should be planned in advance, and it should be ensured that the allocation of the direct labor force for construction is consistent with the construction effort. Accordingly, a manpower plan should be prepared for the key work to be performed by pipefitters and welders.