Research on Reasoning concerning Emergency Measures for Industrial Project Scheduling Control

Table 9

Proposed scheduling control schemes and measures.

SchemeMeasure

Strengthening the principle of the design schemeAdoption of a steel structure design scheme for the process frame
Strengthening the procurement planning for key long-term equipmentSpecification of the time of arrival in the technical agreement portion of the procurement contract
Strengthening the planning of the construction schemeIncreasing the direct construction labor resources (specifically, increasing the numbers of pipefitters and welders)