Research Article
Research on Reasoning concerning Emergency Measures for Industrial Project Scheduling Control
Table 9
Proposed scheduling control schemes and measures.
| Scheme | Measure |
| Strengthening the principle of the design scheme | Adoption of a steel structure design scheme for the process frame | Strengthening the procurement planning for key long-term equipment | Specification of the time of arrival in the technical agreement portion of the procurement contract | Strengthening the planning of the construction scheme | Increasing the direct construction labor resources (specifically, increasing the numbers of pipefitters and welders) |
|
|