Performance of a Large-Scale Excavation by Bottom-Up Technique in Hangzhou Soft Clay
Table 1
Construction schedule of the project.
| Stage | Construction activity | Period (day/month/year) | Zone A | Zone B | Zone C | Zone D |
| 1 | Construction of diaphragm wall | 1/8/2013–10/2/2014 | 2 | Construction of pile foundation | 31/1/2014–15/7/2014 | 3 | Excavation to 2.3 m below the ground and construction of roof slabs | 5/6/2014–20/1/2015 | 4 | Excavation to 7.7 m below the ground | 20/1/2015–5/4/2015 | 20/1/2015–26/4/2015 | 20/1/2015–20/4/2015 | 20/1/2015–25/4/2015 | 5 | Construction of B1 floor slabs | 13/3/2015–24/4/2015 | 1/4/2015–15/5/2015 | 11/4/2015–17/5/2015 | 3/4/2015–14/5/2015 | 6 | Excavation to 13.2 m below the ground | 2/4/2015–15/5/2015 | 17/5/2015–15/6/2015 | 2/5/2015–20/6/2015 | 25/4/2015–9/6/2015 | 7 | Construction of B2 floor slabs | 3/5/2015–3/6/2015 | 9/6/2015–3/7/2015 | 28/5/2015–6/7/2015 | 31/5/2015–27/6/2015 | 8 | Excavation to 22.6 m below the ground | 22/5/2015–16/7/2015 | 3/7/2015–4/8/2015 | 10/6/2015–28/8/2015 | 13/6/2015–18/8/2015 | 9 | Construction of B3 floor slabs | 3/7/2015–8/9/2015 | 23/7/2015–15/8/2015 | 12/8/2015–10/9/2015 | 9/7/2015–23/8/2015 | 10 | Construction of the slabs of excavation | 28/8/2015–15/11/2015 |
|
|