Table 1

Construction schedule of the project.

StageConstruction activityPeriod (day/month/year)
Zone AZone BZone CZone D

1Construction of diaphragm wall1/8/2013–10/2/2014
2Construction of pile foundation31/1/2014–15/7/2014
3Excavation to 2.3 m below the ground and construction of roof slabs5/6/2014–20/1/2015
4Excavation to 7.7 m below the ground20/1/2015–5/4/201520/1/2015–26/4/201520/1/2015–20/4/201520/1/2015–25/4/2015
5Construction of B1 floor slabs13/3/2015–24/4/20151/4/2015–15/5/201511/4/2015–17/5/20153/4/2015–14/5/2015
6Excavation to 13.2 m below the ground2/4/2015–15/5/201517/5/2015–15/6/20152/5/2015–20/6/201525/4/2015–9/6/2015
7Construction of B2 floor slabs3/5/2015–3/6/20159/6/2015–3/7/201528/5/2015–6/7/201531/5/2015–27/6/2015
8Excavation to 22.6 m below the ground22/5/2015–16/7/20153/7/2015–4/8/201510/6/2015–28/8/201513/6/2015–18/8/2015
9Construction of B3 floor slabs3/7/2015–8/9/201523/7/2015–15/8/201512/8/2015–10/9/20159/7/2015–23/8/2015
10Construction of the slabs of excavation28/8/2015–15/11/2015