A Novel Excavation and Construction Method for an Extra-Long Underwater Tunnel in Soft Soils

Table 1

Main construction stages of Zone #1.

StagesConstruction activityDate (mm/dd/year)

1(a)Construction of DSSPs04/01/2018–06/27/2018
1(b)Discharge of lake water and dredging work06/28/2018–07/07/2018
1(c)Construction of bored piles, cut-off walls, and cement mixed piles07/18/2018–09/08/2018
2(a)Removal of embankment or transverse DSSPs09/09/2018
2(b)Excavation of the first layer of subsoil with thickness of 3.2 m09/10/2018–10/16/2018
2(c)Excavation of the second layer of subsoil with thickness of 4 m10/17/2018–12/19/2018
2(d)Installation of struts at Level 112/20/2018–12/31/2018
2(e)Excavation of the third layer of subsoil with thickness of 5.3 m01/01/2019–03/05/2019
2(f)Installation of struts at Level 203/06/2019–03/14/2019
2(g)Excavation of the fourth layer of subsoil with thickness of 3.6 m03/15/2019–04/13/2019
3(a)Casting of floor slabs04/14/2019–06/19/2019
3(b)Removal of struts at Level 206/20/2019–06/27/2019
3(c)Construction of side walls of tunnel06/28/2019–09/09/2019
3(d)Construction of inclined steel struts09/09/2019–09/18/2019
3(e)Removal of struts at Level 109/19/2019–09/26/2019
3(f)Construction of tunnel roof09/27/2019–05/07/2020
3(g)Removal of inclined steel struts05/08/2020–05/21/2020
4(a)Backfilling of soils05/22/2020–05/29/2020
4(b)Construction of earth cofferdam or truncated embankment06/01/2020–06/09/2020
5Removal of longitudinal DSSPs06/20/2020–06/27/2020