Settlement changes of the surface subsidence monitoring point of Junfeng Road Station in different stages.
| Stages of change | Cumulative settlement value (mm) | Cumulative change (mm) | Proportion of total settlement (%) |
| First stage | 0~−6 | 0~−6 | 40 | Second stage | 0~−15 | 0~10 | 40 | Third stage | 0~−15 | 3~12 | 10 | Fourth stage | −10 | 5 | 10 |
|
|