Research Article

System Hazard Analysis of Tower Crane in Different Phases on Construction Site

Table 10

Hazards of system interactions.

Current phasePrevious phaseHazards of system interaction

A1A0HIP55 insufficiency of preparation for tower crane installation

A2A1HUP63 unqualified installation of tower crane
A2HUP64 without maintenance
A3HUP65 unqualified climbing of tower crane

A3A2HCP55 overuse causes breakdown

A4A2HDP55 overuse causes breakdown

Note: A0-Preparation for installation, A1-Installation, A2-Usage, A3-Climbing, A4-Dismantling, as in Figure 3.