Research Article

System Hazard Analysis of Tower Crane in Different Phases on Construction Site

Table 2

Features of tower crane phases.

PhaseTaskPersonnelEquipment

InstallationThe workers assemble the components to install a tower crane.Installers, operator, rigger, signalman, supervisor, and managerTruck crane and other tower cranes
UsageThe workers use a tower crane to lift materials.Operator, rigger, and signalmanTower crane
ClimbingThe workers install a subassembly of the tower crane mast to add the height of the tower crane.Installers, operator, rigger, signalman, supervisor, and managerTruck crane and other tower cranes
DismantlingThe workers dismantle the tower crane to components.Installers, operator, rigger, signalman, supervisor, and managerTruck crane and other tower cranes