Research on Deformation Prediction of Foundation Pit Based on PSO-GM-BP Model
Table 3
Actual value and model fitting value of ZL2-7.
| Period | Actual value | GM (1, 1) | PSO-GM (1, 1) | Fitting value | Relative error (%) | Fitting value | Relative error (%) |
| 1 | 1091.74 | 1091.74 | 0 | 1022.855 | −6.30 | 2 | 1227.01 | 1396.89 | −13.85 | 1397.199 | −13.82 | 3 | 1343.88 | 1468.10 | −9.24 | 1469.021 | −9.31 | 4 | 1578.08 | 1542.94 | −2.23 | 1544.535 | −2.12 | 5 | 1757.89 | 1621.59 | −7.75 | 1623.931 | −7.62 | 6 | 1822.97 | 1704.25 | −6.51 | 1707.408 | −6.33 | 7 | 1828.44 | 1791.12 | −2.04 | 1795.176 | −1.81 | 8 | 1908.81 | 1882.42 | −1.38 | 1887.456 | −1.11 | 9 | 2061.54 | 1978.38 | −4.03 | 1984.479 | −3.73 | 10 | 2025.6 | 2079.23 | −2.65 | 2086.49 | −3.00 | 11 | 2151.51 | 2185.22 | −1.57 | 2193.745 | −1.96 | 12 | 2221.34 | 2296.61 | −3.39 | 2306.513 | −3.83 |
|
|