Case Study on BIM and Value Engineering Integration for Construction Cost Control
Table 11
Potential cost saving as a result of VE and BIM application in ten thousand RMB (USD).
| | Building components | Original cost | Cost after VE and BIM | Difference |
| | Civil engineering | 7766.46 (1143.07) | 6575.20 (967.74) | 1191.26 (175.33) | | Installation project | 3069.31 (451.74) | 3069.31 (451.74) | 0 | | Decoration engineering | 2175.17 (320.14) | 1865.82 (274.61) | 309.35 (45.53) | | Total | 13010.94 (1914.95) | 11510.33 (1694.09) | 1500.61 (220.86) |
|
|