Design and Application of Risk Early Warning System for Subway Station Construction Based on Building Information Modeling Real-Time Model
Table 2
Layout of surveying points for monitoring project.
| Items | Monitoring range | Layout and spacing of surveying points | Accuracy |
| Subsidence | 1–3 times of the ground around the foundation pit and soil in the depth of the foundation pit | 1 every 15–20 m along the longitudinal direction of the station | 0.3 mm | Horizontal displacement and settlement of wall top | Upper of continuous wall | 1 every 15–20 m along the longitudinal direction of the station | 1.5 mm | Wall deformation | Within the enclosure | 20 m spacing and 0.5 m spacing in the same hole in the vertical direction | 1.0 mm | Axial force for support | 1/3 of the steel support between two points at the end | Set for each layer at 30% of support, at least 3 | ≤0.5% (F.S) | Groundwater level | Surrounding of the foundation pit and objects to be protected | Layout in 20–50 m spacing to monitor the section | 10 mm | Settlement and horizontal displacement of surrounding buildings | Buildings (structures) to be protected | Four corners of a building, every 10–15 m along the outer wall | 1.0 mm | Settlement and displacement of underground pipeline | Important municipal pipelines around the foundation pit, such as power tunnel, gas pipe, and water supply pipe | 5–10 m spacing | 0.5 mm | Soil pressure | Within the enclosure | 20 m spacing | ≤0.5% (F.S) | Observation of building cracks | Related building (structures) | It depends | 0.1 mm |
|
|