Research Article

Research on Visual Management Technology of Tunnel Construction Process Based on BIM Technology

Table 3

Overall project schedule.

Job contentStart timeExecution time

Tunnel engineeringTunnel portal reinforcementJuly 10, 2018November 1, 2018
Construction of 1# tunnel open cut sectionOctober 20, 2018May 17, 2019
Tunnel body excavation and initial support of ramp A tunnel and right tunnel entrance of 1# tunnel (single tunnel length 1174.585 linear meters)September 8, 2018December 16, 2019
The second lining, waterproof and drainage, and concrete pavement of ramp A tunnel and right hole entrance of 1# tunnel (single tunnel length 1174.585 linear meters)November 8, 2018March 31, 2020
Tunnel body excavation and initial support of ramp B tunnel and left tunnel entrance of 1# tunnel (single tunnel length 1212 linear meters)October 5, 2018December 11, 2019
The second lining, waterproof and drainage, and concrete pavement of ramp B tunnel and left hole entrance of 1# tunnel (single tunnel length 1212 linear meters)December 5, 2018March 31, 2020
Excavation and initial support at the outlet of the right tunnel of 1# tunnel (single tunnel length 1232 linear meters)November 16, 2018December 9, 2019
The secondary lining, waterproof and drainage, and concrete pavement at the outlet of the right tunnel of 1# tunnel (single tunnel length 1232 linear meters)September 16, 2018March 31, 2020
Excavation and initial support at the outlet of the left tunnel of 1# tunnel (single tunnel length 1265 linear meters)September 25, 2018December 20, 2019
The second lining, waterproof and drainage, and concrete pavement at the outlet of the left tunnel of 1# tunnel (single tunnel length 1265 meters)November 25, 2018March 31, 2020
Excavation and initial support of right entrance of 2# tunnel (single tunnel length 1185 linear meters)September 12, 2018October 28, 2019
The second lining, waterproof and drainage, and concrete pavement at the entrance of the right tunnel of 2# tunnel (single tunnel length 1185 meters)November 12, 2018March 31, 2020
Excavation and initial support of left entrance of 2# tunnel (single tunnel length 1155 linear meters)September 20, 2018September 6, 2019
The second lining, waterproof and drainage, and concrete pavement at the entrance of the left tunnel of 2# tunnel (single tunnel length 1155 meters)November 20, 2018March 31, 2020
Excavation and initial support at the outlet of the right tunnel of 2# tunnel (single tunnel length 1036 linear meters)November 1, 2018October 3, 2019
The secondary lining, waterproof and drainage, and concrete pavement at the outlet of the right tunnel of 2# tunnel (single tunnel length 1036 linear meters)January 1, 2019March 31, 2020
Excavation and initial support at the outlet of the left tunnel of 2# tunnel (single tunnel length 1085.451 linear meters)October 25, 2018December 1, 2019
The secondary lining, waterproof and drainage, and concrete pavement at the outlet of the left tunnel of 2# tunnel (single tunnel length 1085.451 linear meters)December 25, 2018March 31, 2020