Weights of scheme evaluation factors.

Evaluation criteriaNormalized by clusterFactorsNormalized by cluster

Project investment (A)0.3625Construction budget (A1)0.5067
Equipment and installation costs (A2)0.3114
Temporary work cost (A3)0.1179
Land acquisition and immigration costs (A4)0.0640

Scheme reliability (B)0.2779Safety (B1)0.4416
Applicability (B2)0.3972
Durability (B3)0.1612

Construction period (C)0.1082Construction organization design (C1)0.2707
Policy requirement (C2)0.6087
Natural environment (C3)0.1205

Difficulty of construction (D)0.1909Construction technology (D1)0.0891
Construction geological condition (D2)0.2462
Resource allocation (D3)0.6646

Environmental impact (E)0.0605Waste discharge (E1)0.5912
Ecotope (E2)0.2748
Noise (E3)0.1340