Rock mass quality | IV | III | II |
|
Footwall | 1. Shotcrete, bolt, and metal mesh | 1. Shotcrete and bolt | 40 mm thick shotcrete |
| 2. Initial shotcrete within 4 hours after excavation blasting | 2. Initial shotcrete within 3 days after excavation blasting | |
| 3. Install bolt and metal mesh within 12 hours after initial shotcrete | 3. Install bolt within 14 days after initial shotcrete | |
| 4. Secondary shotcrete within 15–20 days after installing bolt and metal mesh | 4. Thickness of shotcrete is 110–120 mm | |
| 5. Thickness of shotcrete is not less than 140 mm | | |
|
| 1. Shotcrete, bolt and metal mesh` | 1. Shotcrete and bolt | |
| 2. Initial shotcrete within 1 day after excavation blasting | 2. Initial shotcrete within 3–5 days after excavation blasting | |
Hanging wall and orebody nearby | 3. Install bolt and metal mesh within 7–10 days after initial shotcrete | 3. Install bolt within 7–10 days after initial shotcrete | — |
| 4. Secondary shotcrete within 20–30 days after installing bolt and metal mesh | 4. Thickness of shotcrete is 40–100 mm | |
| 5. Thickness of shotcrete is 100–140 mm | | |
|
Most orebody | 1. Shotcrete or shotcrete and bolt | | |
| 2. Initial shotcrete within 7 days after excavation blasting | — | — |
| 3. Install bolt within 30 days after initial shotcrete | | |
| 4. Thickness of shotcrete is 40–80 mm | | |
|