Displacement Characteristics of a Deep Excavation in Hangzhou Soft Clay

Table 1

Construction phases and sequence of the excavation.

StageDayConstruction activities

PreexcavationO1Construct diaphragm wall
O2Cast the first concrete prop 1
O3Construct high pressure jet grouting (−18.2 m −22.2 m)
Main excavation (I)A11–8Excavate to level 2 (−5.2 m)
A29–13Install prop 2, prestressed axial force
A314–19SP: excavate to level 3 (−8.5 m)
A420–24NP: cast the concrete prop 2 and waist beam
A525–27SP: install prop 3, prestressed axial force
A628–34Excavate to level 3 (−12.1 m)
A735–37Install prop 3, prestressed axial force
A838–44Excavate to level 4 (−15.65 m)
A945–47Install prop 4, prestressed axial force
A1048–57Excavate to level 5 (−18.2 m)
A1158–60Install prop 5, prestressed axial force
After excavation (II)B161–92SP: construct the second floor and reduce prop 5
B293–119SP: construct the first floor and reduce prop 2,3,4
B3120–125SP: construct the roof of the first floor and reduce prop 1
B461–94NP: construct the second floor and reduce prop 4,5
B595–150NP: construct the first floor and reduce prop 1,2,3