Stage | Day | Construction activities |
|
Preexcavation | O1 | — | Construct diaphragm wall |
O2 | — | Cast the first concrete prop 1 |
O3 | — | Construct high pressure jet grouting (−18.2 m −22.2 m) |
Main excavation (I) | A1 | 1–8 | Excavate to level 2 (−5.2 m) |
A2 | 9–13 | Install prop 2, prestressed axial force |
A3 | 14–19 | SP: excavate to level 3 (−8.5 m) |
A4 | 20–24 | NP: cast the concrete prop 2 and waist beam |
A5 | 25–27 | SP: install prop 3, prestressed axial force |
A6 | 28–34 | Excavate to level 3 (−12.1 m) |
A7 | 35–37 | Install prop 3, prestressed axial force |
A8 | 38–44 | Excavate to level 4 (−15.65 m) |
A9 | 45–47 | Install prop 4, prestressed axial force |
A10 | 48–57 | Excavate to level 5 (−18.2 m) |
A11 | 58–60 | Install prop 5, prestressed axial force |
After excavation (II) | B1 | 61–92 | SP: construct the second floor and reduce prop 5 |
B2 | 93–119 | SP: construct the first floor and reduce prop 2,3,4 |
B3 | 120–125 | SP: construct the roof of the first floor and reduce prop 1 |
B4 | 61–94 | NP: construct the second floor and reduce prop 4,5 |
B5 | 95–150 | NP: construct the first floor and reduce prop 1,2,3 |
|