Research Article
Life Cycle Cost Analysis of Ashore Marine Engine Room
Table 7
Table of cost considering the time value of money (million RMB).
| No. | Name | Payment methods | Period | Option 1 | Option 2 |
| 1 | Design cost | One-time payment | 2013 | 210 | 210 | 2 | Acquisition cost | One-time payment | 2013 | 4315.6 | 5035.8 | 3 | Installation cost | One-time payment | 2013–2017 | 657.8 | 1017.9 | 4 | Operating cost | Equal payment | 2017–2043 | 1828.46 | 1720.63 | 5 | Maintenance cost | Equal payment | 2017–2043 | 127 | 127 | 6 | Environmental cost | Equal payment | 2017–2043 | 50 | 50 | 7 | Scrapping cost | One-time payment | 2017–2043 | 50 | 50 | 8 | Operating years | | | 30 | 30 | 9 | Base rate | | | 6.12% | 6.12% | 10 | Inflation rate | | | 2.60% | 2.60% |
|
|