Research Article

Life Cycle Cost Analysis of Ashore Marine Engine Room

Table 9

Changes in the present value of Option 2 (million RMB).

Uncertainty factorRate of changeValue of cost changePresent LCC valueValue of LCC changeRate of changeSensitivity factor

Basic0.0038294.73
Acquisition cost0.206042.9639301.891007.160.040.18
−0.204028.6437287.57−1007.16−0.040.18
Installation cost0.201221.4838471.84177.110.010.03
−0.20814.3238117.61−177.12−0.010.03
Operating cost0.202064.7644124.225829.490.211.04
−0.201376.5032465.23-5829.50−0.211.04