Optimization of Overcast Stripping Technology Parameters Based on Discrete Event System Simulation
Table 3
Operational efficiency under various operation links.
| Step height (m) | Corresponding step width (m) | Number of digging operations | Average rotation angle (°) | Average digging time (s) | Adjusted average time (s) | Mean time of full load rotation (s) | Average no-load return time (s) | Average operation cycle time (s) |
| 11 | 139.8 | 1614 | 74.05 | 13.00 | 2.44 | 19.57 | 18.73 | 53.73 | 12 | 133.5 | 1661 | 72.54 | 13.01 | 4.91 | 19.42 | 18.54 | 55.88 | 13 | 127.9 | 1682 | 71.88 | 13.02 | 5.07 | 19.35 | 18.43 | 55.86 | 14 | 122.9 | 1689 | 71.87 | 13.01 | 5.19 | 19.31 | 18.37 | 55.89 | 15 | 117.6 | 1687 | 74.05 | 12.97 | 5.29 | 19.99 | 18.95 | 57.21 |
|
|