Research Article

Numerical Simulation Study on Construction Effect of Top-Down Construction Method of Suspended Diaphragm Wall for Deep and Large Foundation Pit in Complex Stratum

Table 3

Details of construction procedures.

Process numberProcess node

1The original stratum is established, and the initial stress is analyzed by applying boundary constraint and self-weight load
2Activate diaphragm wall and clear displacement
3The first excavation to −2.000 m, the first ring frame beam and roof was activated
4The second excavation was to −7.700 m, and the second ring frame beam and the middle slab of the negative first floor were activated
5After the third excavation to −13.400 m, the third ring frame beam and the middle slab of the second floor were activated
6The fourth excavation to −19.750 m, the fourth ring frame beam and the negative third-floor slab were activated
7The fifth excavation to −24.550 m, the fifth ring frame beam and the negative fourth-floor slab were activated
8The sixth excavation was to −28.895 m, and the sixth ring frame beam and the middle slab of the fifth floor were activated
9The seventh excavation was carried out to −34.145 m, and the seventh ring frame beam and the middle slab of the sixth floor were activated
10The eighth excavation to −38.945 m, the eighth ring frame beam and the negative seventh-floor middle plate were activated
11The ninth excavation was carried out to −43.575 m, and the ninth ring frame beam and the middle slab of the eighth floor were activated
12The tenth excavation to −51.630 m, the floor was activated